North Coast Road Stage 2

North Coast Road Stage 2

Reconstruction and upgrade strengthens a key route for Point Turton

Yorke Peninsula Council engaged BildGroup to reconstruct and upgrade North Coast Road Stage 2 at Point Turton, South Australia, marking our first project with the Council.

The works focused on strengthening the road for long-term use. Our team carried out 1.82 kilometres of road stabilisation and 1.82 kilometres of spray sealing, building a solid, durable base and surface for the road. Kerb installation and the construction of three culvert stormwater runs improved drainage along the route, while rock breaking was carried out to prepare the site for construction.

Over the four-month program, from November 2023 to February 2024, we worked closely with the Council to keep the project on track. The project was completed on time and under budget, with zero safety incidents recorded throughout, giving the Council and local community a safer, more reliable road to support the growth of the Yorke Peninsula region.