The Alfred Road Precinct consists of four separate projects in Werribee including Kings Leigh Stage 9C, Kings Leigh Stage 14, Alwood 3A & Ashford Park DCP. The works completed along this stretch of jobs include greenfield subdivision for the adjoining development & the road reconstruction of approximately 600m on Alfred Rd.
This unique project was awarded to BildGroup through hard work and exceptional planning by our project team. We saw the opportunity to provide exceptional value and save time for multiple clients. Liaising with all three clients, we were successful in obtaining approval from local council for a significant road closure to assist in accelerating the works based on our proven track record on similar works.
January 2019
August 2019
>$5M
One of the major differences with this project, was the ability for BildGroup to manage multiple clients simultaneously. BildGroup assisted in reducing copious amounts of risk to the clients by tackling the job wholly rather than individually. This in turn gave BildGroup the ability to overcome constructibility issues that arose between the multiple jobs in a well-planned manner.
We successfully worked within the vicinity of an existing 600mm City West Water feeder main to complete pavement construction and approximately 50 road crossings. This was well planned by the site team and took a lot of diligence.
Construction of multiple retaining walls, one of which was built behind live traffic on Alfred Road, a 90m Concrete Sleeper retaining wall. With limited access, BildGroup had to use alternative methods to excavate and backfill the wall not only to ensure its strength and longevity but with the most important aspect being the safety for all workers and the public.