Lyons Constructions were engaged by Captive Developments to construct a 17-lot residential subdivision in Speciman Hill Rd, Golden Square. Work included excavation and pavement construction, provision of kerb and channel, bituminous surfacing, construction of retaining walls, drainage and bio-retention swales, underground drainage retention tank and associated works.

The Lyons Constructions team was able to seamlessly collaborate with relevant parties to deliver the project on time while concurrently overcoming all challenges faced.

Partners

         

Scope

  • Excavation & Earthworks
  • Pavement – 3500m
  • Kerb and channel – 650m
  • Retaining Walls

Outcomes

  • Worked harmoniously with existing residents
  • Completed the project to a high standard that complied with all local authorities
  • Completed in advance of scheduled timeline