Maiden Gully Contact Us

Bendigo, VIC

The Lyons team were awarded this project in 2020 during the peak of the pandemic to convert a sheep paddock into an 8-lot subdivision. The project incorporated all services including sewer at a depth of 3m, drainage, water and gas reticulation, NBN, electrical provisions and a fire service main.

Our work was completed in advance of the target program with minimal impact to the existing residents and also led into getting repeat work from the consultant.

Partners

       

Scope

  • Excavation & Earthworks
  • Concrete Pavement – 600m
  • Kerb – 300m
  • Utilities – Sewer & Water (Coliban Water), Gas (Ausnet), LV Electrical (Powercor), NBN/Telstra.
  • Stormwater and swale drains

Outcomes

  • Zero environmental impact
  • Streamlined 2-month construction program
  • Completed during the COVID-19 pandemic while adhering to all regulations and safety protocol